Wednesday, April 21, 2010
Tuesday, April 20, 2010
PROJECT UPDATE: KROC COMMUNITY CENTER - GRAND RAPIDS
As the weather warms, Erhardt is heading back outside to complete site work activities, including the sledding hill, basketball and volleyball courts, irrigation pond and miscellaneous seeding. Inside we are continuing with finishes, including ceramic tile, stained and polished concrete, ceiling grid and tile, painting, millwork, acoustical panels in the chapel and many pool elements.
The pool is nearly complete with the soft floor liner being installed this month. Erhardt crews are working on placing the colored slab on grade around the pool.
Erhardt also started work on the elevated track addition to the gymnasium that will continue onto the existing roof of the storage portion of the building. This area will be built up and enclosed with a dramatic aluminum and glass system overlooking the east fields.
The pool is nearly complete with the soft floor liner being installed this month. Erhardt crews are working on placing the colored slab on grade around the pool.
Erhardt also started work on the elevated track addition to the gymnasium that will continue onto the existing roof of the storage portion of the building. This area will be built up and enclosed with a dramatic aluminum and glass system overlooking the east fields.
PROJECT UPDATE: CONSOLATA MISSIONARY SISTERS, BELMONT, MI
All of the new bedrooms and private bathrooms are complete, and painting has started on the second floor. The elevator is nearly complete and the emergency generator was placed earlier this month. The ceramic tile flooring is placed and now is being grouted. The project is ahead of schedule by two weeks and will be ready to re-occupy mid-June.
Due to available projected savings, Erhardt is able to renovate the Sisters’ existing Chapel. Most of their belongings were stored in the Chapel during the renovation and needed to be removed prior to demolition starting. On Friday, April 16, several contractors volunteered their employees’ time and equipment to facilitate moving their furniture from the Chapel. Erhardt supplied lunch and the Sisters brought fresh fruit and ice cream for dessert. In about two hours, the work was done. Special thanks to Heyboer & Bolt, River City Mechanical, and Lenartz Electric for joining Erhardt to make this effort quick and easy!

Due to available projected savings, Erhardt is able to renovate the Sisters’ existing Chapel. Most of their belongings were stored in the Chapel during the renovation and needed to be removed prior to demolition starting. On Friday, April 16, several contractors volunteered their employees’ time and equipment to facilitate moving their furniture from the Chapel. Erhardt supplied lunch and the Sisters brought fresh fruit and ice cream for dessert. In about two hours, the work was done. Special thanks to Heyboer & Bolt, River City Mechanical, and Lenartz Electric for joining Erhardt to make this effort quick and easy!
PROJECT UPDATE: TUNNEL REHABILITATION AT GRAND RAPIDS WASTEWATER TREATMENT PLANT
Erhardt began the Tunnel project in January 2010, and the rehabilitation has been going very well. ECC and trades are coordinating on a daily basis with the City of Grand Rapids to ensure operations continue while their systems are taken on and off line for repair and replacement. The project’s substantial completion date is scheduled for June 1.
Location: Grand Rapids, Michigan
Scheduled Completion: July 1, 2010
Architect / Engineer: Tetra Tech
Monday, April 19, 2010
PROJECT UPDATE: DRUEKE BUILDING
April and May’s work activities include completing the building exterior with windows and doors, and some minor site work. On the interior of the building, drywall has begun along with fixtures and finishes.
Location: Grand Rapids, Michigan
Size: 29,025 SF
Scheduled Completion: May 31, 2010
Architect: Post Associates